eropower.in

Case Study

Advance Electrical design for a 58-Acre Data Center Campus

An In-Depth Case Study on Advanced Electrical Design and Implementation for a 58-Acre State-of-the-Art Data Center Campus Introduction As the world is picking up the pace in digital transformation, data centers have become the backbone of modern businesses, the IT industry, cloud computing and digital infrastructure, which require connectivity and electrical infrastructure that is adaptable and robust. Various factors such as availability of power, efficiency and reliability are important components for data processing, data storage and real time application in a data center, which also result in high power consumption. Due to which large data centers require electrical infrastructure that can assure steady supply of power, regulatory compliance and flexibility in response to varying energy demand. This case study talks about the design of electrical distribution infrastructure of a 58 Acres campus housing various Data Centers buildings including evacuation of power from the grid and design of a 220 kV substation. The 58-acre data center campus represents great engineering excellence to support 12 data center buildings, each with a power demand of 36MW. With a total load demand of more than 400 MW, the project presented multiple challenges, including optimization of space, regulatory compliance and redundancy. This case study provides strategies employed to mitigate various challenges through ingenious electrical design by creation of an underground utility corridor, implementation of a dual power source distribution network and integration of a 220 kV GIS substation. Along with design of the distribution network, the project involved design and execution of a 220 kV GIS substation and a cable terminal tower. An optimized electrical infrastructure required to meet rigorous requirement of the data center industry was designed and implemented through ERO Power’s expertise in electrical design, gird connectivity and distribution planning. Work Scope The 58 Acre Data Center campus had about 12 data center buildings each with a power requirement of 36 MW. The primary work scope included planning of the distribution network in such a way that each building has redundant power sources and each power source is from a different route. Also, the 220kV substation design along with the design of cable termination tower to evacuate power from the grid was the part of the scope. The work scope of the 58-acre data center campus was to design an electrical infrastructure to ensure high availability, scalability and fault tolerance. It involved precise engineering and design of the electrical distribution network, design and commissioning of a 220kV GIS substation, and the execution of power evacuation from the grid. Challenges The 58 Acre Data Center campus presented various challenges during execution of its electrical infrastructure which required critical thinking and innovative engineering solution. Multiple challenges considering the stringent data center requirements were as below. Availability of space. Co-ordination of all required services. Ensuring compliance with statutory guidelines. Allowing flexibility in load pattern and sizing equipment accordingly. Laying high-voltage power cables from dual power sources across a vast data center campus presented several critical challenges, requiring precise coordination and meticulous planning. One major challenge was managing adverse weather conditions, including extreme heat, heavy rainfall, and fluctuating humidity levels. Monsoon seasons caused water accumulation in trenches, delaying excavation and increasing the risk of insulation damage, while temperature variations led to expansion and contraction issues in underground cables, potentially compromising their long-term reliability. Another challenge was routing cables from two independent power sources to twelve data center buildings while ensuring redundancy, safety, and fault tolerance. The need for separate underground routes for each power source made cable alignment complex, requiring careful planning to avoid overlapping pathways or short-circuit risks. Fault conditions required strategic relay protection schemes to isolate affected sections without disrupting the overall power supply. Additionally, integrating high-voltage cables, optical fiber networks, water pipelines, fire system and drainage systems within a shared underground tunnel system introduced further difficulties. Preventing interference between services, ensuring proper clearance, and maintaining accessibility for maintenance while complying with fire safety and ventilation regulations required extensive coordination across multiple engineering disciplines. Various constrains such as limited availability of space for high-capacity electrical equipment, including transformers, switchgear panels, and bus ducts. Given the high-power density of the data center campus, ensuring an optimized equipment layout that conformed to fire safety and maintenance accessibility regulations along with coordination of multiple technical services within the same infrastructure corridor was a significant challenge. The data center campus required seamless integration of electrical, mechanical, HVAC, and networking services, necessitating a highly structured approach to service routing and management. Ensuring compliance with statutory guidelines and obtaining necessary approvals from the regional power distribution authorities posed additional challenges, given the critical nature of grid connectivity and voltage transformation requirements. Additionally, the power distribution network needed to accommodate fluctuating load patterns and future scalability considerations. Data center power demand can vary significantly based on computational workload variations, requiring a design approach that allows for modular expansion while maintaining power quality and stability.  Solutions Equipment was selected with ratings and with appropriate technology to ensure that space usage was optimized. Multiple options of equipment orientation and routes were considered to finalize the space requirements to a minimum and optimum ensuring space for future growth. To resolve the issue of services coordination, it was decided to use a utility tunnel to carry all electrical and other services to various buildings and campus utilities.  This tunnel was placed underground and was designed in a way to ensure easy flow of all services from their entry point to the destination ensuring that: Proper clearances are maintained.  Free space is available for maintenance and addition of future services.  Entry and exit points of services are spaced appropriately to ensure smooth working. Tunnel was well ventilated and all safety systems were installed in the same.  ERO Power was part of the and designing for the electrical distribution was in ERO scope.  ERO Power designed the 220kV substation and the entire electrical distribution in the campus for all the buildings which amounts to designing evacuation of more than 400 MW of power in small area while

Advance Electrical design for a 58-Acre Data Center Campus Read More »

Powering the Future: ERO Power Leads Project Management for Prestigious Data Center’s Substation

Powering the Future: ERO Power Leads Project Management for Prestigious Data Center’s Substation One of a prestigious Data Center Client in Navi Mumbai, a global leader in technology services, is developing the Substation as part of its critical infrastructure to support a data center located in Kalwa, Thane. The Substation is a 220/33kV Gas Insulated Switchgear (GIS) system, designed to provide reliable power supply for the data center, with a proposed total load of 500 MVA over a five-year period. ERO Power LLP played a crucial role as the Project Management Professional (PMP), Consultant, and Services provider, ensuring that the project’s design, regulatory approvals, time management, installation, commissioning, and final charging were executed smoothly. Siemens, as the turnkey contractor, worked in collaboration with ERO Power LLP to deliver the project. Project Overview One of a prestigious Data Center Client in Navi Mumbai, a global provider of information and communication technology (ICT) services, is investing in the development of a 500 MVA substation to support its growing data center operations in Kalwa. The data center’s Substation is designed to provide efficient and scalable power to a campus of 13 buildings over a phased period of five years. To support the growing energy requirements of the data center, two key substations have been established: NAV 2 Substation: Phase I: 220/33kV with two 165 MVA transformers, currently supplying 34 MVA of demand load, with the potential to scale up to 50 MVA. Phase II: A 400/220/33kV setup designed to accommodate the full 500 MVA load in future phases. The Substation (220/33kV GIS): Designed specifically to handle up to 75 MVA of load for the campus. As per the grid connectivity letter dated May 25, 2023, The data Center Client  has been granted grid connectivity for 500 MW across buildings DC 1 to DC 12. ERO Power LLP’s Role as Project Management Professional, Consultant, and Services Provider ERO Power LLP was entrusted with the comprehensive management of the Data Centre’s Substation project. As the Project Management Professional, ERO Power oversaw critical aspects of the project: Design and Regulatory Approval: ERO Power played a pivotal role in ensuring the project design adhered to regulatory standards and obtained necessary approvals for project execution. Time Management: ERO Power ensured that each phase of the project, from design approval to commissioning, adhered to strict timelines. The company facilitated smooth coordination between all stakeholders to ensure project milestones were achieved on time. Installation and Commissioning: ERO Power managed the installation and commissioning process of the substation equipment, ensuring that Siemens and other contractors met the highest standards in execution. Charging:- ERO Power supervised the final charging of the substation, ensuring that all components were successfully integrated and fully operational. Siemens’ Turnkey Contract for Substation Siemens was contracted to deliver the data center’s substation on a turnkey basis. Their responsibilities included the design, engineering, manufacturing, transportation, and installation of the 220/33kV GIS substation. Siemens was also tasked with the civil construction work, ensuring that all components of the substation were integrated seamlessly and efficiently. Key Milestones – Charging Sequence The substation followed a carefully planned charging sequence under the supervision of ERO Power: 18-07-2024: 08:21 p.m: Cable between NTT NAV-2 and data center’s Substation charged 08:33 p.m: 220kV GIS NAV-2 Bus Coupler Bay charged 08:46 p.m: Cable between Kalwa Substation and Substation charged 26-07-2024: 10:30 p.m: 220kV GIS NAV-2 Line Bay charged 11:10 p.m: 220kV GIS Kalwa Line Bay charged 11:27 p.m: Line In Line Out connection for substation completed 29-07-2024: 100 MVA Transformer successfully charged at 08:04 p.m 03-08-2024: 03:50 p.m: 33kV GIS-1 successfully charged 03:59 p.m: 33kV GIS-2 successfully charged 04:00 p.m: 250 KVA Station Transformer successfully charged 14-08-2024: 100 MVA Transformer-2 charged successfully at 03:03 p.m Project Timeline The execution of the data center’s substation project followed this schedule: Drawing & Design Approval: 1.5 months from the issuance of the Work Order Dispatch of Equipment: 8 months from the issuance of the Work Order Installation & Commissioning: 17 months from the issuance of the Work Order ERO Power LLP ensured adherence to these timelines, making sure that all milestones were achieved as per schedule. Contact Us Contact Form NameEmailPhone NumberCompany NameYour MessageSubmit Form Recent Case Study Advance Electrical design for a 58-Acre Data Center Campus Powering the Future: ERO Power Leads Project Management for Prestigious Data Center's Substation Powering Innovation: ERO Power Becomes Exclusive Distribution Operator for SEZ Bio-tech Services ERO Power's Strategic Partnership with Panchshil Realty Share On Facebook Twitter Youtube Linkedin Whatsapp Leave a Reply Cancel Reply Logged in as socialmedia.eropower@gmail.com. Edit your profile. Log out? Required fields are marked * Message*

Powering the Future: ERO Power Leads Project Management for Prestigious Data Center’s Substation Read More »

Powering Innovation: ERO Power Becomes Exclusive Distribution Operator for SEZ Bio-tech Services

Powering Innovation: ERO Power Becomes Exclusive Distribution Operator for SEZ Bio-tech Services In October 2024, ERO Power entered into a 20-year agreement with SEZ Bio-tech Services Pvt Ltd, a subsidiary of the Cyrus Poonawala Group, to serve as the power distribution operator for their Special Economic Zones (SEZs) in Hadapsar and Manjari, Pune, Maharashtra. These SEZs, notable for housing esteemed entities like the Serum Institute, are pivotal in global vaccine production, contributing over 1.5 billion doses annually. citeturn0search0 Objective The primary goal of this partnership is to reduce power costs for clients within the SEZs, thereby enhancing their competitiveness. By ensuring a reliable and cost-effective power supply, ERO Power aims to create a more favorable business environment for companies operating in these zones. Implementation ERO Power will initially manage a power distribution portfolio of approximately 40 MW in these SEZs, with plans to expand this capacity to 75 MW in the near future. The company will oversee the entire power distribution network, providing end-to-end operation and maintenance services, including regular meter testing, daily energy audits, and rigorous safety checks in compliance with OHSAS standards. Innovative Approach This collaboration represents a pioneering move in power distribution within SEZs. By acting as a power distribution operator, ERO Power aims to reduce power costs for clients within the SEZ, thereby enhancing their competitiveness. citeturn0search0 Strategic Impact This partnership is expected to significantly enhance industrial competitiveness and retention in Maharashtra. By lowering power costs and ensuring a reliable power supply, ERO Power is poised to build a more favorable business environment for companies operating in SEZs. citeturn0search0 Client Testimonial Kedar Gokhale, Executive Director of the Cyrus Poonawala Group, remarked, “This is a win-win situation for all stakeholders. One of our initiatives has always been to help the manufacturing facilities inside SEZ to reduce their running costs. Both Hadapsar and Manjari SEZ shall have an added advantage as compared to others biotechnology SEZs regarding their expenses on power now. We are incredibly happy about the services & power domain knowledge of the officials of ERO Power. I am sure they will run the business in very efficient way.” citeturn0search0 Conclusion The agreement between ERO Power and SEZ Bio-tech Services Pvt Ltd exemplifies a strategic initiative to optimize power distribution within specialized economic zones. By leveraging ERO Power’s expertise, the partnership aims to provide sustainable and optimized energy solutions, thereby fostering a more competitive and efficient industrial environment in Maharashtra. Contact Us Contact Form NameEmailPhone NumberCompany NameYour MessageSubmit Form Recent Case Study The Role of Smart Grids in the Future of Power Distribution The Future of Power Distribution in Data Centers: Trends and Innovations Energy Security in IT SEZs: Why Choosing the Right Power Partner is Critical Share On Facebook Twitter Youtube Linkedin Whatsapp Leave a Reply Cancel Reply Logged in as socialmedia.eropower@gmail.com. Edit your profile. Log out? Required fields are marked * Message*

Powering Innovation: ERO Power Becomes Exclusive Distribution Operator for SEZ Bio-tech Services Read More »

ERO Power’s Strategic Partnership with Panchshil Realty

ERO Power’s Strategic Partnership with Panchshil Realty In November 2020, ERO Power, a Mumbai-based energy solutions provider, entered into a 20-year agreement with Panchshil Realty to manage power distribution for Panchshil’s IT/ITES Special Economic Zone (SEZ) in Kharadi, Pune, Maharashtra. Objective The primary goal of this partnership was to supply uninterrupted power to SEZ clients at rates more competitive than those offered by the state utility, Maharashtra State Electricity Distribution Company (MSEDCL). This initiative aimed to reduce operational costs for IT companies, especially during the challenging times of the COVID-19 pandemic. Implementation ERO Power assumed comprehensive responsibilities akin to a distribution licensee, encompassing: Power Procurement: Sourcing electricity at competitive rates to ensure cost efficiency. Network Management: Overseeing the entire power distribution network within the SEZ. Advanced Monitoring: Implementing SCADA-based systems for real-time network monitoring. Automated Metering: Deploying automated meter reading systems to facilitate accurate and hassle-free billing. Outcomes The collaboration yielded significant benefits: Cost Reduction: SEZ clients experienced a decrease in electricity expenses due to the competitive tariffs negotiated by ERO Power. Enhanced Reliability: The implementation of advanced monitoring and metering systems ensured a consistent and reliable power supply. Increased Attractiveness: The cost-effective and reliable power supply enhanced the SEZ’s appeal to potential IT and industrial units. Leadership Atul Chordia, Chairman & Managing Director of Panchshil Realty, expressed confidence in ERO Power’s capabilities, stating, “We are incredibly happy about the services and power domain knowledge of ERO Power. I am sure they will run the business in a very efficient way.” Vandana Bangar Yermalkar, CEO of ERO Power, highlighted the company’s vision: “We are a young startup and wish to transform the power distribution and transmission market. We are very keen on delivering end-to-end solutions to optimize energy costs, smart metering infrastructure, SCADA-based monitoring, and the use of IoT-based devices to maximize efficiency and reduce power T&D losses.” Conclusion The partnership between ERO Power and Panchshil Realty exemplifies a successful collaboration aimed at optimizing energy distribution within a specialized economic zone. By leveraging advanced technologies and strategic management, the initiative not only reduced operational costs for existing clients but also enhanced the SEZ’s attractiveness to prospective businesses. Contact Us Contact Form NameEmailPhone NumberCompany NameYour MessageSubmit Form Recent Case Study The Role of Smart Grids in the Future of Power Distribution The Future of Power Distribution in Data Centers: Trends and Innovations Energy Security in IT SEZs: Why Choosing the Right Power Partner is Critical Share On Facebook Twitter Youtube Linkedin Whatsapp Leave a Reply Cancel Reply Logged in as socialmedia.eropower@gmail.com. Edit your profile. Log out? Required fields are marked * Message*

ERO Power’s Strategic Partnership with Panchshil Realty Read More »

Scroll to Top